On
NW-1, LAD of 2 mtr is being provided between Haldia and Patna for a distance
of 1020 for about 330 days in a year. It is planned to maintain 2 mtr LAD
between Haldia and Patna and 1.5 m between Patna-Varanasi for about 330 days
in a year. On NW-1, floating terminal facilities have been provided by IWAI
at Haldia, Karagola, Bhagalpur, Munger, Patna, Varanasi, Chunar and Allahabad.
Other terminals such as TT Shed and Jugarnath Ghat of CIWTC and permanent
RCC jetties at Farakka and Pakur belonging to Farakka Barrage Project also
exist on this waterway. A scheme for permanent terminal at Gaighat has been
approved and construction work is in progress. Regular talweg surveys are
being conducted and river notices are issued for the entire waterway on fortnightly
basis. Day navigational marks are also being maintained. A scheme for provision
of night navigation facilities between Calcutta and Farakka is also under
implementation. A scheme for procurement of two Cutter Suction Dredging units
for NW-1 is under implementation.
Cargo
Movement